Contract Management for Lee Tunnel
Project
The Thames Tideway Scheme is a huge overhaul of the current sewage system in London, which has seen rapid growth of the capital putting a strain on the current systems that have been in place since the 1800s. Originally as a precautionary method the London sewerage system was designed to allow overflow into the Thames River. This is no longer a viable option, and as such the scheme intends to solve this problem with a 16-mile tunnel running under the Thames, due to open in 2023.
Lee Tunnel is the first phase of this, running from Abbey Mills Pumping Station to Beckton Sewage Treatment Works, the tunnel will collect 16 million tonnes of sewage annually, depositing it at a treatment plant where the reprocessed water can be recycled into the Thames. This project has been the deepest tunnel bored in London to date, exceeding the London Underground and the Crossrail excavations.
Result
Commercial & Contract Management (CONTRACTS) was a key component for this £635m, four-mile long NEC3 ECC Option C project to prevent 16 million tonnes of sewage discharging into the River Lee each year. Completed in 2016, this six-year project benefited from Thinkproject’s collaborative environment for contract administration and reporting. Within Thinkproject over 5,000 communications were administered, each one NEC3 compliant, as well as being accessible, auditable and consistent.